title
A Resolution Awarding the Bid for the Romeo Crossing Community Park Project Phase III
body
WHEREAS, on April 23, 2024, the Village of Romeoville held a bid opening for Phase III of the Romeo Crossing Park Project, at which time the following two base and alternate bids were opened; and
WHEREAS, the apparent low bidder is George’s Landscaping, Inc.; and
WHEREAS, based on its bid as submitted for the base project and alternates, and a review of its bid documents, the recommendation is to award a contract for Phase III of Romeo Crossing Park to George’s Landscaping, Inc. in the amount of $4,432,170.
NOW, THEREFORE, BE IT RESOLVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF ROMEOVILLE, WILL COUNTY, ILLINOIS:
SECTION ONE. The foregoing Recitals are hereby incorporated into this resolution as if fully set forth in this Section 1.
SECTION TWO. That the contract for Phase III of Romeo Crossing Park is hereby awarded to George’s Landscaping, Inc. in the total amount of $4,432,170, subject to Village Manager and Village Attorney review and approval.
SECTION THREE. That the various provisions of this Resolution are to be considered severable and if any part or portion of this Resolution shall be held invalid by any Court of competent jurisdiction, such decision shall not affect the validity of the remaining provisions of this Resolution.
SECTION FOUR. All prior Resolutions and Resolutions, or parts thereof in conflict or inconsistent with this Resolution are hereby expressly repealed only to the extent of such conflict or inconsistency.
SECTION FIVE. This Resolution shall be in full force and effect from and after its passage, approval and publication in pamphlet form as provided by law.